Jharkhand Halts 10 Multi-Village Water Supply Schemes Worth Rs 1,680 Crore Amid Delays

· GlobeWire Daily Public Services Desk · Source: www.livehindustan.com

2 min read

Key takeawaysThe Jharkhand Drinking Water and Sanitation Department has halted 10 multi-village water supply schemes across five divisions, valued at approximately Rs 1,680 crore, after finding them incomplete. The decision follows recommendations from the Advocate General.
Jharkhand Halts 10 Multi-Village Water Supply Schemes Worth Rs 1,680 Crore Amid Delays

Image: www.livehindustan.com · Photo source · Resized and letterboxed to 16:9; no AI generation

The Jharkhand Drinking Water and Sanitation Department has halted 10 multi-village water supply schemes across five divisions, valued at approximately Rs 1,680 crore, after finding them incomplete. The decision follows recommendations from the Advocate General.

These projects were being executed by Chennai-based firm M/s Shriram EPC across Chaibasa, Chatra, Hazaribagh, Dhanbad, and Madhupur. With deadlines having passed years ago for several projects, the department has decided to invite fresh tenders for the remaining work. Funding sources for these 10 schemes include the DMFT fund for five, state funds for four, and the Jal Jeevan Mission for one.

Key Actions and Directives

  • New Tenders: The department will restart the pending work through fresh procurement processes.
  • Warning to Other Agencies: A list of consistently delayed executing agencies is being compiled, with strict directives to complete work by December 2026 or face blacklisting.
  • Ministerial Review: Drinking Water and Sanitation Minister Yogendra Prasad chaired a high-level review meeting at Nepal House, emphasizing that timely public service delivery is a top priority and negligence will not be tolerated.

Status in Selected Divisions

  • Chaibasa: Physical progress for schemes slated for completion in 2022 remains incomplete. For instance, the Chaibasa Aita and Old Chaibasa water supply scheme showed physical progress ranging between 30 and 95 percent, with Rs 36.40 crore spent out of Rs 88.09 crore allocated.
  • Dhanbad: The Govindpur-Nirsa block multi-village scheme faced severe delays. Out of Rs 116.63 crore allocated from Rs 616.93 crore sanctioned, Rs 116.28 crore was spent with 75% work progress reported, but construction was not completed by the target date, and water supply to targeted households has not yet commenced.

Practical Implications and Verification

Citizens awaiting these drinking water connections will experience further delays as new tenders are processed. Stakeholders and citizens can verify official updates and scheme implementation details directly through the official portals of the Jharkhand Drinking Water and Sanitation Department or the Jal Jeevan Mission.

Share this article
Read the original source: झारखंड की 1680 करोड़ की 10 जलापूर्ति योजना पर लगी रोक, क्या थी वजह

AI-assisted reporting; source claims are attributed and have not been independently verified.